Budget: $4,700,000
Status: 95% Construction. Parking lot complete. Installing planting, minor punch-list and demobilization. Deceleration lane base complete. Scheduling concrete.
Construction Start: April 28, 2025
Est. Construction Completion: December, 2025
Scope: New 500 space commuter parking lot with shuttle bus canopies, handicapped and motorcycle parking.
Architect: Garza EMC
Contractor: Falkenberg Construction