Facilities Planning, Design, and Construction (FPDC) is responsible for managing the planning, budgeting, scheduling, programming, design, and construction of Texas State University buildings. Texas State’s pursuit as a growing research institution is fostered through its construction projects, renovations, and infrastructure upgrades. From academics to sports, FPDC benefits all aspects of Texas State.
Capital Project Timeline - Executive Summary (2026-2031)
"Top" 41 Projects (of 180) | Total Estimated Budget: $1.4 Billion | Sorted Chronologically by Projected Substantial Completion (SC) Date. As of: 09/30/2026
Legend:SC = Substantial CompletionDD = Design DevelopmentCIP = Capital Improvement PlanYellow shading = Design phaseGreen shading = Construction phase
| 2026 Q1 | 2026 Q2 | 2026 Q3 | 2026 Q4 | 2027 Q1 | 2027 Q2 | 2027 Q3 | 2027 Q4 | 2028 Q1 | 2028 Q2 | 2028 Q3 | 2028 Q4 | 2029 Q1 | 2029 Q2 | 2029 Q3 | 2029 Q4 | 2030 Q1 | 2030 Q2 | 2030 Q3 | 2030 Q4 | 2031 Q1 | 2031 Q2 | 2031 Q3 | 2031 Q4 | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Centennial Teaching Theater Phase 1 | Academic | $1,200,000 | Aug-26 | LM | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||||||
| JCK 1st floor & One-Stop | Academic | $2,900,000 | Nov-26 | AF | Design phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||||
| STEM | Academic | $137,400,000 | Jan-27 | TM | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||||
| Alkek 6th Floor | Academic | $4,000,000 | Jan-27 | MC | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||||
| ALERRT Center Improvements | Research | $25,000,000 | Jun-27 | LM | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||
| Gymnastics | Athletics | $5,000,000 | Jun-27 | SC | Design phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||||
| Freeman Ranch Test Pad | Research | $250,000 | Jul-27 | DK | Design phase | Design phase | Construction phase | Substantial Completion | ||||||||||||||||||||
| Baseball / Softball Batting & Pitching | Athletics | $4,500,000 | Jul-27 | SJ | Capital Improvement Plan | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||
| Commons Ground Floor Swing Space | Academic | $3,800,000 | Aug-27 | JR | Design phase | Design phase | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||
| Carlson Circle Parking Lot | Parking | $6,000,000 | Aug-27 | KR | Design phase | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||
| Esperanza Phase 2 | Academic | $25,000,000 | Aug-27 | LM | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||||
| Comanche Pedestrian Bridge | Infrastructure | $4,000,000 | Aug-27 | TM | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||||
| Centennial Teaching Theater Phase 2 | Academic | $2,700,000 | Aug-27 | LM | Design phase | Design phase | Construction phase | Substantial Completion | ||||||||||||||||||||
| Hilltop 2 w/ Dining (Juniper & Verbena) | Student Success | $280,000,000 | Aug-27 | BD | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | Construction phase | Substantial Completion | |||||||||||||||
| Round Rock Parking lot | Parking | $4,000,000 | Jan-28 | KR | Capital Improvement Plan | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||
| Comal Renovation for New Dean | Academic | $2,000,000 | Jan-28 | DC | Capital Improvement Plan | Design phase | Design phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||||
| Music Building Lobby Renovation | Academic | $7,200,000 | Jun-28 | MC | Capital Improvement Plan | Design phase | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||
| Spring Lake Site Improvements | Outdoor | $10,000,000 | Jun-28 | SC | Design phase | Design phase | Design Development | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||
| Hotel at Texas State (DB P3) | Special | $70,000,000 | Aug-28 | SC | Design phase | Design phase | Design Development | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||
| West Stadium Suite Addition | Athletics | $6,000,000 | Aug-28 | SJ | Capital Improvement Plan | Design phase | Design phase | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||
| Star Two | Research | $41,100,000 | Sep-28 | SJ | Design phase | Design phase | Design phase | Design Development | Design phase | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||
| Baseball / Softball - Locker Rooms | Athletics | $12,000,000 | Dec-28 | SJ | Capital Improvement Plan | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||
| Charles Austin Parking Garage | Parking | $32,400,000 | Dec-28 | BD | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||
| East Chiller Plant Renewal | Infrastructure | $10,000,000 | Jun-29 | TC | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||||
| Sewell Park Improvements | Outdoor | $20,000,000 | Jun-29 | SC | Capital Improvement Plan | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||
| Round Rock Residence Hall (P3) | Student Success | $30,000,000 | Jun-29 | BD | Capital Improvement Plan | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||
| DERRICK/MCS Reno & Wing Removal | Academic | $10,000,000 | Aug-29 | GB | Design phase | Design phase | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||
| Chautauqua Event Lawn | Academic | $15,000,000 | Aug-29 | GB | Design phase | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||
| Music Building Expansion | Academic | $14,000,000 | Aug-29 | LM | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||||||
| Construction Management at Star Park | Academic | $10,000,000 | Aug-29 | SJ | Capital Improvement Plan | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||
| University Health Services Expansion | Student Success | $18,000,000 | Dec-29 | TM | Capital Improvement Plan | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||
| Theater Center Renovation/Expansion | Academic | $43,200,000 | Jan-30 | GB | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||||||
| Spring Lake Visitor Center / Wittliff | Special | $40,000,000 | Apr-30 | GB | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| Emergency Shelter / Field House (CCAP) | Athletics | $30,000,000 | Jun-30 | SJ | CCAP Request | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| Discovery Building (CCAP) | Academic | $226,800,000 | Aug-30 | TM | CCAP Request | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| Round Rock University Commons (CCAP) | Academic | $110,000,000 | Aug-30 | LM | CCAP Request | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| STEM Parking Garage (CCAP) | Parking | $21,600,000 | Aug-30 | TM | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | ||||||||||||
| ALERRT Center Improvement - Phase 2 | Research | $25,000,000 | Aug-30 | CCAP Request | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| ALERRT West Texas Training Center - Sul Ross | Research | $32,300,000 | Aug-30 | CCAP Request | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | Substantial Completion | |||||||||||
| Chemistry Renovation - After Discovery | Academic | $30,000,000 | Aug-32 | GB | Capital Improvement Plan | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | |||||||||||||
| Live Oak Parking Garage *** | Parking | $29,100,000 | Aug-32 | GB | Capital Improvement Plan | Design phase | Design phase | Design phase | Design Development | Design phase | Construction phase | Construction phase | Construction phase | Construction phase | Construction phase | |||||||||||||
For additional inquiries, reach out to Amy Thomas by email at08@txstate.edu or phone 512-245-1547.