Esperanza Hall is the fourth academic building on the Round Rock Campus. It includes a large, tiered classroom, general classrooms, study spaces, lounge areas, conference room and vending. The phase 1 construction includes the build-out of classrooms/study/lounge space on floor 1, and shell space for future build-out on floors 2 & 3.
Budget: $52,409,972
Status: Construction – 70%. Roof decking installation complete/insulation underway.
Est. Construction Start: November 15, 2024
Substantial Completion: June 05, 2026 (Phase 1)
Scope: New 81,621 SF academic building to house general classrooms, and faculty/staff offices.
Architect: BGK Architects
Contractor: Joeris Construction