Castro Residence Hall is a new student community providing amazing views, close access to food service and recreation venues, and a convenient location along the campus shuttle, pedestrian mall, and future STEM Building.
The 7-story residence hall is comprised of 942 beds. Amenities in the facility include a large student commons area, student lounge, student kitchen, seminar room, collaborative study rooms, package delivery pickup, gaming rooms, and laundry room.
Budget: $124M
Status: Construction – 89% Complete. Site work underway. Fire Alarm rough-in nearing completion. Building punch as started. Elevator installation underway.
Est. Construction Start: December 12th, 2023
Phase I Est. Construction Completion: July 15th 2025
Phase II Est. Construction Completion: Est. January 2026
Scope: Construction of a seven-story residential structure with central community area, comprised of 221,678gsf, and accommodating 942 beds.
Design-Builder: SpawGlass/RSA